Produktionstechnik

Optimized production for customer markets of the future

  • Decommissioning of the GWA earlier than planned
  • Ramp-up of the new facilities planned from May 2025
  • Focus on premium grades for lightweight construction and high surface quality as well as electrical steel grades

thyssenkrupp Steel Europe is pressing ahead with the modernization of its production facilities at the Duisburg site. As part of the Strategy 20-30, the casting and rolling line, which has been in operation for over 25 years, was taken out of operation this evening and will be replaced by a state-of-the-art continuous casting line and a modernized hot strip mill. These measures are taking place two weeks earlier than planned and mark a significant milestone for sustainable and innovative steel production at the Duisburg site. The ramp-up of the new continuous casting line 4 and hot strip mill 4 with two new walking beam furnaces is scheduled as of May 2025.

Focus on customer markets of the future

‘As planned, we are continuing to make targeted investments to strengthen our Duisburg site,’ explains Dennis Grimm, Spokesman of the Executive Board of thyssenkrupp Steel. ‘With the fundamentally modernized hot strip mill 4 and the conversion and new construction of continuous casters 3 and 4, we are setting the course for our future viability, especially in terms of efficiency and profitability. By separating and converting our casting androlling line, we are making our production network more flexible and increasing the availability of our systems. We are thus preparing ourselves for the coming requirements of our customers in target markets that are important to us, such as mobility and energy.’

By optimizing its production network, thyssenkrupp Steel is continuing to focus its product portfolio on future markets and profitable premium products. These include multiphase steels and lightweight steels as well as grades with high surface quality. In addition, the production of high-quality electrical steel grades, which are indispensable for the energy and mobility transition, will be strengthened. 

Firmenkontakt und Herausgeber der Meldung:

thyssenkrupp Steel Europe AG
Kaiser-Wilhelm-Str. 100
47166 Duisburg
Telefon: +49 (203) 52-0
Telefax: +49 (203) 52-25102
http://www.thyssenkrupp-steel-europe.com

Ansprechpartner:
Mark Stagge
SE/COM
Telefon: +49 (203) 52-25159
E-Mail: mark.stagge@thyssenkrupp.com
Für die oben stehende Story ist allein der jeweils angegebene Herausgeber (siehe Firmenkontakt oben) verantwortlich. Dieser ist in der Regel auch Urheber des Pressetextes, sowie der angehängten Bild-, Ton-, Video-, Medien- und Informationsmaterialien. Die United News Network GmbH übernimmt keine Haftung für die Korrektheit oder Vollständigkeit der dargestellten Meldung. Auch bei Übertragungsfehlern oder anderen Störungen haftet sie nur im Fall von Vorsatz oder grober Fahrlässigkeit. Die Nutzung von hier archivierten Informationen zur Eigeninformation und redaktionellen Weiterverarbeitung ist in der Regel kostenfrei. Bitte klären Sie vor einer Weiterverwendung urheberrechtliche Fragen mit dem angegebenen Herausgeber. Eine systematische Speicherung dieser Daten sowie die Verwendung auch von Teilen dieses Datenbankwerks sind nur mit schriftlicher Genehmigung durch die United News Network GmbH gestattet.

counterpixel